AWP Labs · How eight bids and an itemized list were made comparable
Owner fictional · demo tenderPackages A (3 bids) · B (5 bids)8 P6 schedules · fictional data
How the eight bids and the Owner's itemized list were made comparable before any adherence check. Fictional case; real method.
The challenge was translation, not analysis. Eight schedules, five contractors and an itemized
list with its own codes: before anything could be compared, everything had to speak the same language.
↻ The whole process
Two inputs, one common language, two clean-ups in parallel, three checks and the dashboards.
? What had to be translated
Each problem, its fix, and the stage where it was solved.
1 One standard classification · 16 disciplines
The same catalogue for each bidder's labor, equipment and materials and for the itemized lines.
01Site establishment
02Earthworks
03Civil works
04Structural steel
05Mechanical
06Boilermaking & plating
07Piping
08Electrical
09Instrumentation & control
10Architecture
11Insulation & painting
12Hydraulics & wells
13Underground works
14Support services & rigging
15Precommissioning & start-up
16Subcontracts & transport
2 Equalize every bidder's resources
Only what has a validated physical unit enters the comparison.
3 Clean the Owner's itemized list
A struck-through line is withdrawn scope: measuring against it inflates the demand.
4 Check adherence on three axes
Each axis answers a different question and is reported separately.
5 Show it in comparative dashboards
The standardized data feeds six comparative dashboards.
Standardizing
is the deliverable, not a preliminary: without the catalogue no comparison holds.
Unit discipline
never add across categories; convert only what is unambiguous (kg → t).
Clean both sides
a coverage figure is only as honest as the baseline it is measured against.
Multi-axis adherence
scope, resources and network quality, never collapsed into one score.
DSH-SAS-13 · Bid standardisation process - one page of flowcharts (static demo)comparative · 8 objects
REV-TEC-02 Bid-leveling standardisation process map - the five stages as flowcharts
CMP-GEN-14 16-discipline homologation catalogue for tender resource levelling (cross-cutting standard)
REV-GEN-10 Strikethrough exclusion audit - cell formatting read as contractual state
REV-GEN-11 Owner itemizado vs bidder P6 quantities - coverage by discipline
KPI-GEN-05 Standard DCMA-14 engine (the 14 official checks)